2019/10/24: progress report

We’re delighted to report that the ferry passed today’s MCA safety inspection. The final elements of the work are underway, ahead of tomorrow’s tow inspection. Our tow back is sea condition restricted & scheduled to take place overnight this coming Sunday. Weather permitting, we’ll be back in Sandbanks early on Monday 28th October for final …

2019/10/24: progress report Read More »

2019/10/23: progress report

Yesterday saw a successful day’s work with great progress made. Today, we’ve been installing the segments on the second wheel and completing the associated welding work, ready for their testing tomorrow and an MCA inspection.

2019/10/22: PROGRESS REPORT

Following yesterday’s work on fitting the shafts and couplings, today and tomorrow will see the fitting of the segments to the ferry’s drive wheels and the preparation of the ferry for MCA and insurance sign-off later this week, prior to the planned tow back to Dorset.

2019/10/21: PROGRESS REPORT

Work has been continuing throughout the weekend and today at the repair facility in Southampton. The engineer from the Swedish component manufacturer is on site to provide expert guidance during these final stages of the repair.